PSS #97
Updated by Sieu Ngo about 1 month ago
Flushed every "Even Year" - prefer during April and May.
MH1
MH2
MH4 - COMPLETED BY PAUL 3/28/26
MH5 - COMPLETED BY PAUL 3/28/26
MH6
MH7 - COMPLETED BY PAUL 3/28/26
MH8 - COMPLETED BY PAUL 3/28/26
MH9
MH10
MH11
KP1
KP2
KP3
KP4
KP5 - NEW Lowes WH installed 03/26
KP6
KP7
KP8
WR - COMPLETED BY PAUL 3/28/26
PSS - 2 Heaters, need to be done same time
DC Broiler Room -
DC Restaurant -
WI B1:
WI B2: Old Unit Pulled from BI, flushed at Nov 2025 during install, next due: April 2028
WI B3, Unit 1:
WI B3, Unit 2: B3:
W1:
BI MAIN / NOT ACTIVE
BI OFFICE / NOT ACTIVE
NOTE: NEXT FLUSH WILL BE IN 2028 / NEEDS TO BE DONE DURING MONTH OF APRIL AND MAY
MH1
MH2
MH4 - COMPLETED BY PAUL 3/28/26
MH5 - COMPLETED BY PAUL 3/28/26
MH6
MH7 - COMPLETED BY PAUL 3/28/26
MH8 - COMPLETED BY PAUL 3/28/26
MH9
MH10
MH11
KP1
KP2
KP3
KP4
KP5 - NEW Lowes WH installed 03/26
KP6
KP7
KP8
WR - COMPLETED BY PAUL 3/28/26
PSS - 2 Heaters, need to be done same time
DC Broiler Room -
DC Restaurant -
WI B1:
WI B2: Old Unit Pulled from BI, flushed at Nov 2025 during install, next due: April 2028
WI B3, Unit 1:
WI B3, Unit 2: B3:
W1:
BI MAIN / NOT ACTIVE
BI OFFICE / NOT ACTIVE
NOTE: NEXT FLUSH WILL BE IN 2028 / NEEDS TO BE DONE DURING MONTH OF APRIL AND MAY