Project

General

Profile

PSS #97

Updated by Sieu Ngo about 1 month ago

Flushed every "Even Year" - prefer during April and May. NEED TO FLUSH ONCE A YEAR DURING SUMMER

MH1
MH2
MH4 - COMPLETED BY PAUL 3/28/26
MH5 - COMPLETED BY PAUL 3/28/26
MH6
MH7 - COMPLETED BY PAUL 3/28/26
MH8 - COMPLETED BY PAUL 3/28/26
MH9
MH10
MH11

KP1
KP2
KP3
KP4
KP5 - NEW Lowes WH installed WATER HEATER / BRAND NEW PURCHASED 03/26
KP6
KP7
KP8

WR - COMPLETED BY PAUL 3/28/26

PSS - THERE ARE ONLY 2 Heaters, need to be done same time UNITS FOR THE BUILDING, AND THEY NEED TO BE DONE AT THE SAME TIME.

DC Broiler Room - MAIN
DC Restaurant - RESTUARANT

WI B1: B1
WI B2: B2
WI B3: B3

W1:

BI MAIN / NOT ACTIVE
BI OFFICE / NOT ACTIVE

WASH ON FIRST - Ask mar/steve by monday/tuesday 3/30 or 3/31, to flush the water heater

NEED TO COMPLETE THIS ON OR BEFORE JUNE 1, 2026


NOTE: NEXT FLUSH WILL BE IN 2028 / NEEDS TO BE DONE DURING MONTH OF APRIL AND MAY